Injuries increase on smart motorway scheme

08/09/2021 | CHRIS AMES

A new report on a smart motorway section of the M1 has revealed that the absolute number of personal injury collisions rose during the last two years of the period studied to a level higher than the annual average before the scheme opened.

National Highways excluded casualty figures for the fourth and fifth years from its five-years-after post opening project evaluation of the dynamic hard shoulder (DHS) scheme between junctions 10 and 13 of the M1, which opened in December 2012.

It is not clear why this happened. Although the report cites the change in casualty severity reporting that took place in 2016, this only affected the balance between serious and slight casualties, not the overall number of personal injury collisions or the number of collisions resulting in fatalities.

However, the report does disclose that there were an annual average of 95 personal injury collisions over the five-year period after the scheme was operational compared with 98 before the scheme.

The total number of such incidents in the first three years after opening was 272. Based on the annual average of 95, there were 475 incidents over five years, meaning that during the last two years there were a total of 203 incidents, an average of 101.5. This is therefore higher than the pre-scheme annual average of 98.

The figures appear to support the idea that collision rates on smart motorways increase as the additional space produced by the extra lane, which is temporary in dynamic hard shoulder running, is taken up by additional traffic.

A one-year after opening evaluation of smart motorway schemes between junctions 28 and 35a of the M1 states that 'traffic levels are set to increase in later years' and acknowledges the possibility that this could impact initially positive safety data.

Although the report does not appear to give traffic volumes for each year after opening, it does show that they increased overall, from an average 5,700 vehicles per hour in the pm peak (1,900 vehicles per lane as a three-lane motorway) to 6,300 vehicles per hour, which was 2,100 vehicles per as a three-lane motorway but just under 1,600 vehicles per lane with the fourth lane in operation.

The increase in traffic volumes meant that casualty rates per vehicle kilometre improved to a greater extent than indicated by absolute casualty figures.

The report also discloses that the number of serious collisions nearly doubled from 19 in the three years before the scheme was built to 32 in the three years after opening. This was not affected by the change in reporting.

It also states that there were five more collisions leading to serious injuries per year after the scheme, although this may have been affected by reporting changes.

The number of fatalities was three (an average of one a year), which was the same as in the three year period before work started on the scheme. No fatality figure is given for the fourth and fifth years, although a separate report shows that a further fatal collision occurred in the fifth year.

The two reports came to light following an FOI request from Highways. Transport minister Baroness Vere told the Transport Select Committee in June that she hoped to supply the reports in approximately two weeks but their publication stalled since then.

It was released at the same time as an evaluation by the Office of Rail and Road of Highways England’s use of statistics, which found that although the government-owned company had made no fundamental errors there is a limited amount of data available.

In 2019, there were only 141 miles of all lane running motorway (ALR), the network having expanded from 29 miles in 2014, which means that only 29 miles of ALR has a full five years’ worth of data.

The ORR also found that high-level statistics making comparisons between conventional motorways and smart motorways did not always separate the types of road between controlled motorways, DHS and, ALR ‘which may have obscured the impact of the removal of the hard shoulder’.

DHS schemes, which are to be phased out, operate as conventional motorways for most of the time and calculating the overall safety performance of DHS schemes is likely to dilute any reduction in safety that arises when the hard shoulder is used as a running lane.

This effect may be increased by the fact that when used as a conventional motorway, DHS schemes have the additional benefit of emergency refuge areas, which allow some drivers to leave the hard shoulder in an emergency.

Highways InProfile

latest magazine issue
Highways jobs

Senior Structures Technician

£32,654 - £36,124 plus circa £2000 - £4000 OT (variable
To lead on the planning, delivery and reporting of the highway structures General Inspection programme. Baglan, Port Talbot
Recruiter: South Wales Trunk Road Agent

Assistant Director of Place Operations

to £115,452
Bury is a proud and prosperous borough Bury, Greater Manchester
Recruiter: Bury Council

Career Grade Transport Planner (Carer Grade 6-8)

Grade 06 (£29,093 - £32,654) TO Grade 08 (£37,938 - £41,511)
This is a fantastic opportunity to work for a forward thinking and dynamic transport authority located in the heart of the North West Warrington, Cheshire
Recruiter: Warrington Borough Council

Principal Performance and Assurance Manager

£Competitive
We have an exciting opportunity for a highly motivated Principal Performance and Assurance Manager to join our Senior Management Team SBIM Avonmouth, Bristol
Recruiter: Amey

Principal Construction Manager

£Competitive
We are excited to offer a fantastic opportunity for a Permanent Principal Construction Manager to join our dynamic Area 12 West Yorkshire
Recruiter: Amey

Electrician

£Competitive
We are excited to offer a fantastic opportunity for two Permanent Electricians Tingley, Wakefield
Recruiter: Amey

Asset Development Manager

£44,111 per annum (pay award pending)
Do you want to work for an organisation that values you as an individual? West Yorkshire
Recruiter: West Yorkshire Combined Authority

Principal Engineer – Structures Capital Delivery

£43,693 - £47,754
To act as one of the Agent's technical experts for highway structures schemes and related issues South Wales
Recruiter: South Wales Trunk Road Agent

Senior Engineer Programme Management

£36,124 - £39,513
To support the Principal Engineer ensuring effective co-ordination, programming and contract administration. South Wales
Recruiter: South Wales Trunk Road Agent

Highways Capital Lead

£47,754 - £50,788
To be responsible for management of the Regional Highway Capital Delivery Teams South Wales
Recruiter: South Wales Trunk Road Agent

Senior Engineer – Structures Delivery

£36,124 - £39,513
To support the Principal Engineer Structures (Capital Works) and deputise if necessary South Wales
Recruiter: South Wales Trunk Road Agent

Senior Engineer – Structures Condition

£36,124 - £39,513 plus circa £2500 - £4000 OT (variable)
To take the lead role on the Structures Principal and General Inspection programmes South Wales
Recruiter: South Wales Trunk Road Agent

Senior Development Management Engineer

£37,938 - £44,711
In line with our One Coventry Values, we want to ensure that our communities are represented across our workforce Coventry, West Midlands
Recruiter: Coventry City Council

Senior Engineer (Consultancy)

£43,693 - £50,788 
In line with our One Coventry Values, we want to ensure that our communities are represented across our workforce Coventry, West Midlands
Recruiter: Coventry City Council

Carbon and Net Zero Manager

£47,754 - £50,788
To lead and manage the carbon strategy for the Agent by developing a programme South Wales
Recruiter: South Wales Trunk Road Agent

Highways Engagement Officer - WMF1977e

£33,366 - £34,314
The role will provide specialist support within the Highways service Kendal, Cumbria
Recruiter: Westmorland and Furness Council

Trunk Road Services – Senior Supervisor

Grade 9
South Wales Trunk Road Agent
Recruiter: South Wales Trunk Road Agent

Horticultural Operative

£25390.0000 - £26203.0000 per annum
Essex County Council (ECC) are delighted to be supporting Braintree Council to recruit a Horticultural Operative.To apply please click here
Recruiter: Essex County Council

Highway Asset Maintenance Assistant Engineer (CDC)

Grade 8, £32,662 - £36,239 (Pay award pending)
The City of Doncaster Council is a confident, ambitious organisation Doncaster, South Yorkshire
Recruiter: City Of Doncaster Council

Engineer, Highways Asset Maintenance CDC

Grade 9, £38,653 - £42,728 (Pay award pending)
The City of Doncaster Council is a confident, ambitious organisation which puts improving the life of its residents at the centre of everything we do. Doncaster, South Yorkshire
Recruiter: City Of Doncaster Council
SUBSCRIBE NOW

Latest Video

Subscribe to Highways today to ensure you keep your finger on the pulse of everything happening in the UK road network throughout the year.

SUBSCRIBE NOW