Council slams Highways England over A47 delays

27/01/2020 | CHRIS AMES

Norfolk County Council has called for Highways England to be held to account for the ‘agonisingly slow’ progress on improvements to the A47.

The council has told regulator the Office of Rail and Road (ORR) of its ‘major concern’ that work promised in 2014 and due for completion this year has not even started.

The schemes are:

  • The Great Yarmouth junctions
  • Blofield to Burlingham dualling
  • Thickthorn junction
  • Easton to Tuddenham dualling

In 2017 Highways England announced that the Easton to North Tuddenham, Blofield to North Burlingham and Thickthorn Junction schemes were to be delayed as part of a wider reprofiling of the current Road Investment Strategy that has seen around 10% of its schemes delayed, kicked into the long grass or cancelled.

The ORR is currently consulting public bodies on how it holds Highways England to account.

The council’s proposed response points out that £300m worth of improvements were due to be completed during the current Road Investment Strategy (2015 to 2020).

On the drawing board: A route image for the A47 Blofield to North Burlingham scheme

Martin Wilby, cabinet member for highways and infrastructure, said: ‘The Government approved the funding in 2014 and Highways England should be completing improvements to the A47 this year – but it has not even started work.

‘Norfolk is missing out on economic growth, new homes and jobs because of this continued delay. It’s unacceptable and we want the regulator to intervene early in cases like this.’

The council said it is concerned that the revised construction start dates of 2021/22 will not be met.

A Highways England spokesperson said: ‘We share the Norfolk County Council’s eagerness so see the upgrades delivered as soon as possible and value their support as we take each scheme through its development.’

The government-owned company said it has been developing the schemes through the current RIS period for delivery between 2020 and 2025.

The Blofield to North Burlingham and A47 North Tuddenham to Easton schemes are currently set to start work in spring 2022 while the Thickthorn junction upgrade is expected to start in spring next year.

The start date for the Great Yarmouth junctions scheme is still to be confirmed.

All four schemes were in fact listed as part of the current RIS, rather than to be ‘developed for the next Road Period’. 

The council report states: ‘The expectation when the Government announced the inclusion of the A47 schemes within the programme for 2015-2020 was that they would be constructed within that period. We have, however, yet to see a start on any of the schemes.’

‘Progress in development and delivery of the schemes has been agonisingly slow. Norfolk is extremely concerned about the ability of Highways England to deliver such projects.’

The council said it is encouraging the ORR, when faced by issues like this, to ‘meaningfully intervene’ at an early stage, and seek an early resolution.

The report will be considered by the infrastructure and development select committee on Wednesday (29 January), before being considered by the cabinet on 3 February.

Highways InProfile

latest magazine issue
Highways jobs

Highways Capital Lead

£47,754 - £50,788
To be responsible for management of the Regional Highway Capital Delivery Teams South Wales
Recruiter: South Wales Trunk Road Agent

Senior Development Management Engineer

£37,938 - £44,711
In line with our One Coventry Values, we want to ensure that our communities are represented across our workforce Coventry, West Midlands
Recruiter: Coventry City Council

Head of Highways

£66,366 - £85,284 pa
Highway Operations is a large division within the Planning, Growth & Infrastructure. Enfield (City/Town), London (Greater)
Recruiter: Enfield London Borough Council

Circular Economy Officer - FTC till the 31st March 26

£26526.00 - £31208.00 per annum + + 26 Days Leave & Local Gov Pension
... England, Essex, Chelmsford
Recruiter: Essex County Council

Director Highways, Transport & Waste Management

up to £120k
There for Nottinghamshire. There for each other. There for you. Nottinghamshire
Recruiter: Nottinghamshire County Council

Director of Highways and Transportation

£126,909
We’re seeking a dynamic and innovative leader to spearhead our Highways and Transportation services. Essex
Recruiter: Essex County Council

Senior Structures Technician

£32,654 - £36,124 plus circa £2000 - £4000 OT (variable
To lead on the planning, delivery and reporting of the highway structures General Inspection programme. Baglan, Port Talbot
Recruiter: South Wales Trunk Road Agent

Assistant Director of Place Operations

£85,962 to £93,267
Bury is a proud and prosperous borough Bury, Greater Manchester
Recruiter: Bury Council

Career Grade Transport Planner (Carer Grade 6-8)

Grade 06 (£29,093 - £32,654) TO Grade 08 (£37,938 - £41,511)
This is a fantastic opportunity to work for a forward thinking and dynamic transport authority located in the heart of the North West Warrington, Cheshire
Recruiter: Warrington Borough Council

Principal Performance and Assurance Manager

£Competitive
We have an exciting opportunity for a highly motivated Principal Performance and Assurance Manager to join our Senior Management Team SBIM Avonmouth, Bristol
Recruiter: Amey

Principal Construction Manager

£Competitive
We are excited to offer a fantastic opportunity for a Permanent Principal Construction Manager to join our dynamic Area 12 West Yorkshire
Recruiter: Amey

Electrician

£Competitive
We are excited to offer a fantastic opportunity for two Permanent Electricians Tingley, Wakefield
Recruiter: Amey

Asset Development Manager

£44,111 per annum (pay award pending)
Do you want to work for an organisation that values you as an individual? West Yorkshire
Recruiter: West Yorkshire Combined Authority

Principal Engineer – Structures Capital Delivery

£43,693 - £47,754
To act as one of the Agent's technical experts for highway structures schemes and related issues South Wales
Recruiter: South Wales Trunk Road Agent

Senior Engineer Programme Management

£36,124 - £39,513
To support the Principal Engineer ensuring effective co-ordination, programming and contract administration. South Wales
Recruiter: South Wales Trunk Road Agent

Senior Engineer – Structures Delivery

£36,124 - £39,513
To support the Principal Engineer Structures (Capital Works) and deputise if necessary South Wales
Recruiter: South Wales Trunk Road Agent

Senior Engineer – Structures Condition

£36,124 - £39,513 plus circa £2500 - £4000 OT (variable)
To take the lead role on the Structures Principal and General Inspection programmes South Wales
Recruiter: South Wales Trunk Road Agent

Senior Engineer (Consultancy)

£43,693 - £50,788 
In line with our One Coventry Values, we want to ensure that our communities are represented across our workforce Coventry, West Midlands
Recruiter: Coventry City Council

Carbon and Net Zero Manager

£47,754 - £50,788
To lead and manage the carbon strategy for the Agent by developing a programme South Wales
Recruiter: South Wales Trunk Road Agent

Highways Engagement Officer - WMF1977e

£33,366 - £34,314
The role will provide specialist support within the Highways service Kendal, Cumbria
Recruiter: Westmorland and Furness Council
SUBSCRIBE NOW

Latest Video

Subscribe to Highways today to ensure you keep your finger on the pulse of everything happening in the UK road network throughout the year.

SUBSCRIBE NOW