Aberdeen junction works blown behind schedule

06/01/2022 | CHRIS AMES

The expected completion of the Scottish Government’s £18m A92/A96 Haudagain Improvement has been put back to the spring.

The Haudagain Roundabout is a major road junction in Aberdeen. In 2019 Farrans, a sister company of Tarmac and part of CRH was awarded a £17.6m design and build contract by Transport Scotland to reconfigure the junction.

An earlier view of the project, which is now 'well advanced'

Minister for transport Graeme Dey said the project is ‘well advanced and remains within budget’.

However, Transport Scotland said pandemic impacts, supply chain issues and recent storms had combined to push back timescales, with the project now opening to traffic by the end of March 2022.

The pandemic continued to disrupt progress this year with key work having to be rescheduled due to the impact on workforces.

Transport Scotland added that industry-wide supply chain issues affected the availability of materials hitting timescales despite the contractor taking mitigation measures by re-sequencing work and sourcing from alternative suppliers.

A large proportion of the remaining work, including road surfacing, could not be carried out during recent adverse weather including storm Arwen and Barra.

Mr Dey added: ‘The contractor has reported impacts to programme critical work within the previous month due to adverse weather from Storm Arwen and Storm Barra. Until these recent events, our contractor had been able to maintain an anticipated completion date within the Winter 2021 period, despite the challenges posed throughout 2021 by the ongoing COVID-19 pandemic and industry-wide supply chain issues.

‘We have consistently highlighted the potential risk such events could have in causing a delay to the expected completion date for this project. Likewise this revised date remains subject to no further disruption from events such as adverse weather or impacts from the ongoing pandemic.’

Highways InProfile

latest magazine issue
Highways jobs

Senior Structures Technician

£32,654 - £36,124 plus circa £2000 - £4000 OT (variable
To lead on the planning, delivery and reporting of the highway structures General Inspection programme. Baglan, Port Talbot
Recruiter: South Wales Trunk Road Agent

Assistant Director of Place Operations

to £115,452
Bury is a proud and prosperous borough Bury, Greater Manchester
Recruiter: Bury Council

Career Grade Transport Planner (Carer Grade 6-8)

Grade 06 (£29,093 - £32,654) TO Grade 08 (£37,938 - £41,511)
This is a fantastic opportunity to work for a forward thinking and dynamic transport authority located in the heart of the North West Warrington, Cheshire
Recruiter: Warrington Borough Council

Principal Performance and Assurance Manager

£Competitive
We have an exciting opportunity for a highly motivated Principal Performance and Assurance Manager to join our Senior Management Team SBIM Avonmouth, Bristol
Recruiter: Amey

Principal Construction Manager

£Competitive
We are excited to offer a fantastic opportunity for a Permanent Principal Construction Manager to join our dynamic Area 12 West Yorkshire
Recruiter: Amey

Electrician

£Competitive
We are excited to offer a fantastic opportunity for two Permanent Electricians Tingley, Wakefield
Recruiter: Amey

Asset Development Manager

£44,111 per annum (pay award pending)
Do you want to work for an organisation that values you as an individual? West Yorkshire
Recruiter: West Yorkshire Combined Authority

Principal Engineer – Structures Capital Delivery

£43,693 - £47,754
To act as one of the Agent's technical experts for highway structures schemes and related issues South Wales
Recruiter: South Wales Trunk Road Agent

Senior Engineer Programme Management

£36,124 - £39,513
To support the Principal Engineer ensuring effective co-ordination, programming and contract administration. South Wales
Recruiter: South Wales Trunk Road Agent

Highways Capital Lead

£47,754 - £50,788
To be responsible for management of the Regional Highway Capital Delivery Teams South Wales
Recruiter: South Wales Trunk Road Agent

Senior Engineer – Structures Delivery

£36,124 - £39,513
To support the Principal Engineer Structures (Capital Works) and deputise if necessary South Wales
Recruiter: South Wales Trunk Road Agent

Senior Engineer – Structures Condition

£36,124 - £39,513 plus circa £2500 - £4000 OT (variable)
To take the lead role on the Structures Principal and General Inspection programmes South Wales
Recruiter: South Wales Trunk Road Agent

Senior Development Management Engineer

£37,938 - £44,711
In line with our One Coventry Values, we want to ensure that our communities are represented across our workforce Coventry, West Midlands
Recruiter: Coventry City Council

Senior Engineer (Consultancy)

£43,693 - £50,788 
In line with our One Coventry Values, we want to ensure that our communities are represented across our workforce Coventry, West Midlands
Recruiter: Coventry City Council

Carbon and Net Zero Manager

£47,754 - £50,788
To lead and manage the carbon strategy for the Agent by developing a programme South Wales
Recruiter: South Wales Trunk Road Agent

Highways Engagement Officer - WMF1977e

£33,366 - £34,314
The role will provide specialist support within the Highways service Kendal, Cumbria
Recruiter: Westmorland and Furness Council

Trunk Road Services – Senior Supervisor

Grade 9
South Wales Trunk Road Agent
Recruiter: South Wales Trunk Road Agent

Horticultural Operative

£25390.0000 - £26203.0000 per annum
Essex County Council (ECC) are delighted to be supporting Braintree Council to recruit a Horticultural Operative.To apply please click here
Recruiter: Essex County Council

Highway Asset Maintenance Assistant Engineer (CDC)

Grade 8, £32,662 - £36,239 (Pay award pending)
The City of Doncaster Council is a confident, ambitious organisation Doncaster, South Yorkshire
Recruiter: City Of Doncaster Council

Engineer, Highways Asset Maintenance CDC

Grade 9, £38,653 - £42,728 (Pay award pending)
The City of Doncaster Council is a confident, ambitious organisation which puts improving the life of its residents at the centre of everything we do. Doncaster, South Yorkshire
Recruiter: City Of Doncaster Council
SUBSCRIBE NOW

Latest Video

Subscribe to Highways today to ensure you keep your finger on the pulse of everything happening in the UK road network throughout the year.

SUBSCRIBE NOW